Online leak repair for of reduce temperature line Furnace 1

  • Survey, calculate data, design, process and manufacture Clamp.
  • Install clamp, glue injection for online leak sealing of reduce temperature line.

Pipe line parameters:

- Pressure: 100 bar.

- Temperature: 200 degrees Celsius.

Online leak repair for of reduce temperature line Furnace 1

Leak point before repair - An Khanh Thermal Power Plant

Online leak repair for of reduce temperature line Furnace 1

The leak point was completely sealed after repairing - An Khanh Thermal Power Plant

Other Projects

WHR Turbine  -  Generator Overhaul

WHR Turbine - Generator Overhaul

View more
Repair and replace GRP pipe systems

Repair and replace GRP pipe systems

View more
Heat exchanger flanges re-surfacing

Heat exchanger flanges re-surfacing

View more
Bolting service for mechanical equipment - TA 2023

Bolting service for mechanical equipment - TA 2023

View more
Overhaul of Residual Heat Boiler No. 1

Overhaul of Residual Heat Boiler No. 1

View more
Cleaning, welding  for leak sealing of equipment E04504

Cleaning, welding for leak sealing of equipment E04504

View more